Project Planning Engineer at PRINCIPAL BUILDERS - Engineers & Contractors
After scheduling a baseline of any project in P6, we oftenly export cash flow. My question is, what date does P6 take as cutt off date for monthly cash flow for your project.
If time span of project is 12 months, P6 will give you a cumulative cash flow till 12th month. What date of the month does P6 take as a cutoff date when we draw S-Curve. Actually when I draw it manually in excel it gives different values and when I schedule P6 for my monthly reports it give different values.
Forexample: if you schedule P6 for 3rd month schedule % is 15.52% and when I check it from activity usage profile it is giving the value of 16.21%.
Os usuários precisam estar logados para escrever comentários
Entrar
Responder
Já tem Oracle Primavera?
Sobre Oracle Primavera
Por mais de 30 anos, projetos bem-sucedidos ao redor do mundo têm confiado nas soluções Primavera da Oracle Construction and Engineering para planejar, construir e operar ativos críticos. É a única so
Com mais de 2,5 milhões de avaliações, podemos fornecer os detalhes específicos que ajudam você a tomar uma decisão de compra de software informada para o seu negócio. Encontrar o produto certo é importante, deixe-nos ajudar.
ou continuar com
LinkedIn
Google
Google (Negócios)
Endereços do Gmail.com não permitidos. Um domínio empresarial usando o Google é permitido.