What is the best way to carry our EVA in Primavera P6.

The Project schedule forecasts better if we have a detailed breakup of tasks. However, if we have a detailed breakup of the tasks, it is difficult to assign cost to these activities as the costs are available at a much higher level of the Project BOQs. Additionally, putting actual cost is also a difficult tasks.
1 comment
Looks like you’re not logged in.
Users need to be logged in to answer questions
Log In
Rahmat H.
RH
Shariah Business Management, Project Control & Risk Management in EPC Oil & Gas Industry, e-Price Action
0
IMO, Earned Value Analysis is better and useful if performed in high level.